A Red Letter Day!

FoSG coordinator Peter Becker shows Mayor Joseph Solomon and Gov. Gina Raimondo plans for the new playground.

Governor Gina Raimondo and Warwick Mayor Joseph Solomon visited Salter Grove on Tuesday, May 22nd, to celebrate the award of a $100,000 community recreation grant from the Department of Environmental Management (DEM) to the City of Warwick. Together with donations from individuals and businesses previously collected by FoSG, the grant will enable replacement of the existing 40-year old playground.

Continue reading

Contractor Selected to Repair Causeway

On May 21st, the Warwick City Council approved the contractor selected to repair the causeway at Salter Grove with a $200,000 budget; namely, Narragansett Dock Works (NDW) in partnership with GZA GeoEnvironmental, Inc.

NDW plans to install a prefabricated concrete box culverts at the sites of the displaced footbridge near the breakwater and the existing plastic culverts. The new culverts may be sized approximately 5 feet wide and 4 feet deep to maintain water flow between the north and south sides of the causeway, and to act as bridges.

Depending on the available funding, the elevation of the causeway path may be raised to prevent overtopping during higher tides, and thus provide safer passage for pedestrians.

Permits will be required from the Coastal Resources Management Council, the Rhode Island Department of Environmental Management, and the US Army Corps of Engineers before construction can start, hopefully in late summer.

Good Turnout for Salter Grove Cleanup on April 29

Despite morning rain on Sunday, April 29, over 30 volunteers showed up to make Salter Grove even more beautiful by removing trash in all sectors of the park.

This enjoyable event led to over 400 pounds of trash being collected. The trash was picked up the following Monday by the City of Warwick. Good job everyone!

Continue reading

Contractors Briefed on Causeway Repair

UPDATE 3/3/18: Bids of three contractors were accepted on April 2nd.

Warwick engineers Eric Earls (yellow jacket) and Eric Hindinger (motioning) brief contractors about causeway repair at Salter Grove.

Warwick Engineers Eric Earls and Eric Hindinger briefed representatives from 14 companies interested in bidding on repair of the causeway at Salter Grove. The obligatory briefing on March 5th started in the Council Chambers at City Hall and finished on site at George B. Salter Memorial Grove.

Earls advised contractors to focus on the low-lying area near the plastic culverts and the deep cut previously crossed by a foot bridge, which he described as “treacherous” at high tide. The focus should be on providing safe access to the breakwater, with any other improvements being “gravy.”

Continue reading

RFP for Causeway Repair Posted!

This slideshow requires JavaScript.

On February 14th, the City of Warwick posted a Request for Proposals (RFP) to repair the causeway connecting Salter Grove to the breakwater.

The proposal’s scope of work includes the design, permitting, and construction of improvements to the causeway to improve access to the breakwater. At a minimum, the areas currently containing culverts and a displaced footbridge superstructure, which are flooded at high tide, are to be repaired.

Continue reading

Phase I Fundraising Goal Exceeded!

We closed last year with nearly $8,000 raised to replace the playground equipment at Salter Grove—one third more than our goal. Thank you all for your generous support!

We raised $2,281 from the sale of raffle tickets and netted $4,572.50 from individual donations, We also received a $1,000 legislative grant via Sen. Michael McCaffrey. Some of these funds passed though our fiscal sponsor, the New England Grassroots Environment Fund.

Continue reading